1. Even during the rains and floods, Polavaram Project construction continues uninterruptedly
  2. Currently, 19 lakh cusecs of flood water flowing from Godavari river
  3. MEIL executing the works with all precautionary measures
  4. So far, 44 girders have been fixed on 11 blocks
  5. Slab construction work is going on these 11 blocks
  6. 2 lakh cubic metres of concrete work completed in the spillway
  7. 1.10 lakh cubic metres of concrete work completed in spill channel
  8. Hill excavation, concrete dam construction, earth removing works are at a brisk pace
  9. With sufficient workers and modern machinery, the project works are progressing