Another Motor Dry Run Held At Kaleshwaram Pump House

The dry run of another motor-pump, fourth one so far, of the Kaleshwaram project Package-8 pump house at Laxmipur in Karimnagar was taken up successfully on Friday by the engineers.About 65 per cent of works in Medigadda barrage and 85 per cent each in Annaram and Sundilla barrages have been completed as part of Kaleshwaram Lift Irrigation Project. As far as the progress of work in Medigadda is concerned, two of the 11 pumps are ready for dry run.