MEIL Readies 220 KV Substation at Annaram

This Video is bring to notice that 220 KV Substation of Annaram Pump House was Successfully charged under the Kaleshwaram Lift Irrigation Scheme.The substation is located at Peddapalli district, Manthani Mandal, Gunja Padugu Village. The 220/11KV Annaram Substation is constructed for providing power supply to Annaram pump house. The substation consists of 10 Nos of 50 MVA Transformers. 220 KV TMDC Transmission Line of 28 KM is laid from 400/220/11kV Sundilla Substation to 220/11kV Annaram Substation.